The Town works to update the public on construction plans and the status of various projects. During construction season, weekly updates are issued outling the status of various projects and the focus of work for the coming week.

Construction Updates

Construction Project Update: September 20, 2019

Ongoing construction projects in the Town of Paradise for the period of September 23-27 include:

  • Lift Station (St. Thomas Line – Topsail Road):  The external equipment is operational and crews are assessing the situation to determine the work plan and timeline for the repairs.  The pumper trucks are no longer needed on site.  They may be periodically required depending on the nature of the work. At times, there may be traffic interruptions, as equipment and trucks work in the area. 
  • Topsail Road Roundabout: Traffic interruptions and delays are expected at the roundabout for the next two weeks as the work moves to the medians and centre islands. Due to the nature of this portion of work, traffic will be impacted and delayed throughout the day. Efforts will be made to minimize impact on traffic flow, however, at times delays will occur, including during the morning and evening commute. If possible, residents are advised to find alternate routes. All drivers are asked to use caution in the area and to follow signage and traffic control procedures.

Weather permitting, paving operations for the surface layer of asphalt for Topsail Road / McNamara Drive roundabout are scheduled for Saturday, September 20. Traffic will be delayed throughout the day, and if possible, residents are advised to find alternate routes.  

The Topsail Road / McNamara Drive roundabout project is on schedule and is anticipated to be completed by mid Fall. 
  • Paradise Road: Work continues on installing sidewalks. Traffic delays can be expected for sections of Paradise Road, near Camrose Drive and at Stormont Street, due to ongoing sanitary trunk sewer and water main installation. Please note that the section of Paradise Road between Archibald Drive and Camrose Drive will not be paved at this time due to upcoming water and sewer work in the area. The section of road will be paved before the end of the construction season. 
  • Camrose Drive Access: Access to Camrose Drive via Paradise Road will be unavailable beginning 7 a.m. Thursday, September 19 until Tuesday,  September 24. Access to Camrose Drive will be available via Deborah Lynn Heights on St. Thomas Line. The access closure is needed as part of the Paradise Road Upgrades Phase III. 
  • Topsail Road Sidewalk Work: Sidewalk work is taking place for a section of Topsail Road, Sunvalley Drive to Paradise Road. To accommodate the work, the inside curb lane in the area is closed. In the morning, traffic flow will be maintained eastbound with minimal interruptions until 9:00 a.m. and in the evening, traffic flow westbound will be maintained with minimal interruptions beginning at 4:00 p.m.
  • Donna Road: Driveway reinstatement is underway and is expected to be completed in the next couple of weeks. All drivers are asked to use caution in the area and to follow signage and traffic control procedures.
  • Adams Pond Trail: Work continues on the final section of the trail and the project is expected to be completed by the end of October. The existing section of trail is open to users with barricades placed at the construction area. Residents are asked to follow all signage and please avoid the construction area.
  • Clearview Heights: Preparatory work for the first layer of asphalt is being completed and sidewalk installation has started. The detour is in place for the duration of this construction project. 
  • Paradise Double Ice Complex Renovations: Interior renovations are taking place at the Complex, to relocate the reception area to the front of the building, near the main doors of the building. No impact to operations or programming at the facility while the work is ongoing. It is expected to be completed by the end of October. Users are asked to follow all posted signage and to please avoid the immediate construction area. 
  • Archibald Drive and Stormont Street: Sanitary trunk sewer and water main installation is taking place in the area of Archibald Drive and Stormont Street to connect into Lanark Drive. Some of the work is taking place in undeveloped areas and near the Adams Pond Trail. Residents are asked to respect all posted signs and avoid the construction area. The work is expected to be completed by the end of October. 
  • Line Painting is currently taking place throughout the Town. 
Construction Project Update: September 9, 2019
Ongoing construction projects in the Town of Paradise for the period of September 9-13 include:
  • Lift Station (St. Thomas Line – Topsail Road): The external equipment is installed and the pumper trucks are no longer needed on site. Periodically, pumper trucks may be required depending on the nature of the work. Crews are working to empty the lift station and assess the situation to determine next steps. At times, there may be traffic interruptions, as equipment and trucks work in the area. 
  • Topsail Road Roundabout: Work continues on the entry islands of the roundabout. Efforts are made to keep traffic flowing as best as possible but delays may occur for Topsail Road and McNamara Drive. The Town advises residents to utilize the “zipper merge” technique in order to most effectively move traffic and reduce delay times. This project remains on schedule with anticipated completion in mid fall.
  • Paradise Road: The first layer of asphalt is in place. Work continues on installing sidewalks. Please note that the section of Paradise Road between Archibald Drive and Camrose Drive will not be paved at this time due to upcoming water and sewer work in the area. The section of road will be paved before the end of the construction season. 
  • Evergreen Village and Donna Road: Road repairs are finished in Evergreen Village. Work continues on Donna Road and is expected to be completed in the next couple of weeks. These areas are local roads and minimal traffic disruptions are anticipated. All drivers are asked to use caution in the area and to follow signage and traffic control procedures.
  • Adams Pond Trail: Work continues on the final section of the trail and the project is expected to be completed by the end of October. The existing section of trail is open to users with barricades placed at the construction area. Residents are asked to follow all signage and please avoid the construction area.
  • Clearview Heights: Work for curb and gutter is scheduled to begin this week. The detour is in place for the duration of this construction project. 
Regular Street upgrades / paving and water and sewer work are ongoing throughout the construction season. 
Construction Porject Update: August 30, 2019

Ongoing construction projects in the Town of Paradise for the period of September 3-6 include:

  • Lift Station (St. Thomas Line – Topsail Road): Emergency repairs continue at the sanitary sewer lift station. Equipment is being installed on site and when that is operational, pumper trucks will not be needed. Once the additional equipment working, the lift station can be fully emptied, and crews can assess the situation to determine next steps. At times, there may be traffic interruptions, as equipment and trucks work in the area. 
  • Topsail Road Roundabout: The first layer of asphalt is complete. Work will now focus on the installation of curb for the entry islands of the roundabout. Efforts are made to keep traffic flowing as best as possible and delays can be expected for Topsail Road and McNamara Drive. The Town advises residents to utilize the “zipper merge” technique in order to most effectively move traffic and reduce delay times. This project remains on schedule with anticipated completion in mid fall.
  • Paradise Road: The first layer of asphalt is in place and this project remains ahead of schedule. Work next week will focus on installing sidewalks. Please note that the section of Paradise Road between Archibald Drive and Camrose Drive will not be paved at this time due to upcoming water and sewer work in the area. The section of road will be paved before the end of the construction season. 
  • Topsail Road (Kemount Road Overpass to Carlisle Drive):  This project is completed.  
  • Evergreen Village and Donna Road: Road repairs are ongoing for Evergreen Village and Donna Road. Road work will occur daily on weekdays from 7 a.m. to 7 p.m. and is expected to take three to four weeks to complete. These areas are local roads and minimal traffic disruptions are anticipated. All drivers are asked to use caution in the area and to follow signage and traffic control procedures.
  • Adams Pond Trail: Work continues on the final section of the trail and the project is expected to be completed by the end of October. The existing section of trail is open to users with barricades placed at the construction area. Residents are asked to follow all signage and please avoid the construction area.
  • Clearview Heights: Road upgrades continue and the detour is in place for the duration of this construction project. 

Regular Street upgrades / paving and water and sewer work are ongoing throughout the construction season. 

Construction Project Update: August 23, 2019 
Ongoing construction projects in the Town of Paradise for the period of August 26-30 include:
  • Lift Station (St. Thomas Line – Topsail Road): Emergency repairs continue at the sanitary sewer lift station located on the corner of St. Thomas Line and Topsail Road. At this time, there is no direct impact to residents in Paradise, residents can still use their bathrooms and flush toilets. Preparatory site work is being completed for equipment that is being shipped to the Town to eliminate the need for continual use of pump trucks and enable repairs to be completed.  To facilitate the work, the curb lane on St. Thomas Line is closed.
  • Topsail Road (Kemount Road Overpass to Carlisle Drive): This project is expected to be completed early next week, weather pending.  While work is ongoing, during the morning commute, two-lane traffic flow is maintained eastbound with minimal interruptions until 9:00 a.m. and during the evening commute, beginning at 4:00 p.m. two-lane traffic flow westbound is maintained with minimal interruptions. Businesses in the area remain open during the construction period.
  • Evergreen Village and Donna Road: Road repairs are ongoing for Evergreen Village and Donna Road. Road work will occur daily on weekdays from 7 a.m. to 7 p.m. and is expected to take three to four weeks to complete. These areas are local roads and minimal traffic disruptions are anticipated. All drivers are asked to use caution in the area and to follow signage and traffic control procedures.
  • Topsail Road Roundabout: Work will focus on the installation of curb for the entry islands of the roundabout. Efforts are made to keep traffic flowing as best as possible and delays can be expected for Topsail Road and McNamara Drive. The Town advises residents to utilize the “zipper merge” technique in order to most effectively move traffic and reduce delay times. This project remains on schedule with anticipated completion in early fall.
  • Clearview Heights: Road upgrades continue and the detour is in place for the duration of this construction project. 
  • Paradise Road: Paving operations have started on Paradise Road and this project is ahead of schedule. Please note that the section of Paradise Road between Archibald Drive and Camrose Drive will not be paved at this time due to upcoming water and sewer work in the area. The section of road will be paved before the end of the construction season. Drivers are asked to use caution in the area, reduce speeds and follow all signage in the area. 
  • Adams Pond Trail: Work continues on the final section of the trail and the project is expected to be completed by the end of October. The existing section of trail is open to users with barricades placed at the construction area. Residents are asked to follow all signage and please avoid the construction area.
Line Painting, Regular Street upgrades / paving and water and sewer work are ongoing throughout the construction season. 
 
Construction Project Update: August 16, 2019

Ongoing construction projects in the Town of Paradise for the period of August 19-23 include:

  • Lift Station (St. Thomas Line – Topsail Road): Emergency repairs continue at the sanitary sewer lift station located on the corner of St. Thomas Line and Topsail Road. At this time, there is no direct impact to residents in Paradise, residents can still use their bathrooms and flush toilets. This lift station is for the sewer system, so there is no impact on the water system. To facilitate the work, a section of St. Thomas Line, from Topsail Road to Carlingford Street, is closed and traffic is diverted through Carlingford Street. Traffic calming measures are in place. 
  • Topsail Road (Kemount Road Overpass to Carlisle Drive): Road work is ongoing on Topsail Road between the Kenmount Road overpass and Carlisle Drive. During the morning commute, two-lane traffic flow is maintained eastbound with minimal interruptions until 9:00 a.m. and during the evening commute, beginning at 4:00 p.m.  two-lane traffic flow westbound is maintained with minimal interruptions. Businesses in the area remain open during the construction period.
  • Topsail Road Roundabout: Construction is ongoing and at this time the area is reduced to one lane in each direction. The traffic lights are removed from the intersection and traffic is moving in a roundabout configuration. Efforts are made to keep traffic flowing as best as possible and delays can be expected for Topsail Road and McNamara Drive. The Town advises residents to utilize the “zipper merge” technique in order to most effectively move traffic and reduce delay times.
  • Clearview Heights: Road upgrades continue and the detour is in place for the duration of this construction project. 
  • Paradise Road: Work continues for Phase III upgrades for Paradise Road for the section of road between Stormont Street and Archibald Drive. Traffic delays are expected with this type of road project. During construction hours, there is only one lane of traffic as the nature of the work makes it impossible to maintain a lane of traffic in each direction. Once construction concludes each day, there are two lanes of traffic. Drivers are asked to use caution in the area, reduce speeds and follow all signage in the area. 
  • Adams Pond Trail: Work continues on the final section of the trail and the project is expected to be completed by the end of October. The existing section of trail is open to users with barricades placed at the construction area. Residents are asked to follow all signage and please avoid the construction area.
Line Painting, Regular Street upgrades / paving and water and sewer work are ongoing throughout the construction season. 
Construction Project Update: August 9, 2019
Ongoing construction projects in the Town of Paradise for the period of August 12-16 include:
  • Topsail Road (Kemount Road Overpass – Carlisle Drive): On Monday, August 12, work will begin on Topsail Road in the area between the Kenmount Road overpass and Carlisle Drive. Work will include completing the retaining wall; curb, gutter and sidewalk, and road repair. During the morning rush hour, two-lane traffic flow is maintained eastbound with minimal interruptions until 9:00 a.m. and during the evening rush hour, two-lane traffic flow westbound is maintained with minimal interruptions beginning at 4:00 p.m. Outside of these times, lane closures will be implemented as needed and traffic delays are expected. Drivers are asked to use caution in the area, reduce speeds and follow all signage in the area.  Please note that area businesses will remain open during the construction period.
  • Topsail Road Roundabout: The traffic lights are removed from the Topsail Road / McNamara Drive intersection and traffic is moving in a roundabout configuration. Construction is ongoing and at this time the area is reduced to one lane in each direction. Efforts will be made to keep traffic flowing as best as possible and delays can be expected for Topsail Road and McNamara Drive. The Town advises residents to utilize the “zipper merge” technique in order to most effectively move traffic and reduce delay times.
  • McNamara Drive: Paving operations for McNamara Drive have been completed. Work is scheduled to begin on shouldering during this period.
  • Clearview Heights:  Road upgrades continue and the detour is in place for the duration of this construction project. 
  • Paradise Road: Work continues for Phase III upgrades for Paradise Road for the section of road between Stormont Street and Archibald Drive. Traffic delays are expected with this type of road project. During construction hours, there is only one lane of traffic as the nature of the work makes it impossible to maintain a lane of traffic in each direction. Once construction concludes each day, there are two lanes of traffic and the temporary traffic lights are no longer in service. Drivers are asked to use caution in the area, reduce speeds and follow all signage in the area. 
  • Adams Pond Trail: Work continues on the final section of the trail and the project is expected to be completed by the end of October. The existing section of trail is open to users with barricades placed at the construction area. Residents are asked to follow all signage and please avoid the construction area.
Line Painting, Regular Street upgrades / paving and water and sewer work are ongoing throughout the construction season. 
Construction Project Update: August 2, 2019

Ongoing construction projects in the Town of Paradise for the period of August 5-9 include:

  • Topsail Road Roundabout: The traffic lights are removed from the Topsail Road / McNamara Drive intersection and traffic is moving in a roundabout configuration. Construction is ongoing and at this time the area is reduced to one lane in each direction. Efforts will be made to keep traffic flowing as best as possible and delays can be expected for Topsail Road and McNamara Drive.
  • McNamara Drive: Paving operations for McNamara Drive are scheduled to begin on Monday, August 5, weather permitting. This is for the final layer of asphalt to complete the water and sewer work completed earlier the summer. 
  • Clearview Heights: Road upgrades continue and the detour is in place for the duration of this construction project. 
  • Paradise Road: Work continues for Phase III upgrades for Paradise Road for the section of road between Stormont Street and Archibald Drive. Traffic delays are expected with this type of road project. During construction hours, there is only one lane of traffic as the nature of the work makes it impossible to maintain a lane of traffic in each direction. Once construction concludes each day, there are two lanes of traffic and the temporary traffic lights are no longer in service. Drivers are asked to use caution in the area, reduce speeds and follow all signage in the area. 
  • Adams Pond Trail: Work continues on the final section of the trail and the project is expected to be completed by the end of October. The existing section of trail is open to users with barricades placed at the construction area. Residents are asked to follow all signage and please avoid the construction area.

Line Painting, Regular Street upgrades / paving and water and sewer work are ongoing throughout the construction season. 

Construction Project Update: July 26, 2019 

Ongoing construction projects in the Town of Paradise for the period of July 26 – August 2 include:

  • Topsail Road Roundabout: Effective Tuesday, July 30 the traffic lights will be removed from the intersection and traffic will flow in a roundabout configuration. At this time, the roundabout will be one lane to accommodate the ongoing construction work for the project. Traffic control, including flagpersons and appropriate signage, will be in place to direct drivers. Traffic on Topsail Road will merge into one lane to enter the roundabout and drivers are encouraged to use the zipper merge technique to assist with traffic flow. With this portion of work, traffic will be continually flowing through the area, under the direction of traffic control. Efforts will be made to reduce traffic impacts, especially during the evening and morning commute times.
  • Clearview Heights:  Road upgrades continue and the detour is in place for the duration of this construction project. 
  • Paradise Road: Work continues for Phase III upgrades for Paradise Road for the section of road between Stormont Street and Archibald Drive. The ditches have been filled to create as much room as possible for traffic through the construction zones. Traffic delays are expected as the nature of this work makes it impossible to maintain a lane of traffic in each direction all the times.
  • Adams Pond Trail: Work continues on the final section of the trail and the project is expected to be completed by the end of October. The existing section of trail is open to users with barricades placed at the construction area. Residents are asked to follow all signage and please avoid the construction area.
  • Peter Barry Duff Memorial Park: All major construction work is complete and the Park is open for full use. Some work remains to be completed by NF Power and the lights are not yet operational. Park users are asked to follow any posted signage and avoid any identified work areas.  

Line Painting, Regular Street upgrades / paving and water and sewer work are ongoing throughout the construction season. 

Construction Project Update: July 19, 2019
Ongoing construction projects in the Town of Paradise for the period of July 22-26 include:
  • Topsail Road Roundabout: Work continues in the Topsail Road –McNamara Drive intersection and as a result the traffic lights are deactivated daily at 7 a.m. and returned to service by 6 p.m. Traffic control is in place while the lights are deactivated. Traffic flow is maintained during this portion of work – in the morning, traffic flow is maintained eastbound with minimal interruptions until 9:00 a.m. and in the evening, traffic flow westbound is maintained with minimal interruptions beginning at 4:00 p.m. Please note that traffic delays may occur at 9 a.m. and 6 p.m. when traffic changeovers occur and traffic control measures change. Access to Paradise Plaza from Topsail Road is right turn only, all other traffic can access via McNamara Drive. 
  • Clearview Heights: Road upgrades continue and the detour is in place for the duration of this construction project. 
  • Paradise Road: Work continues for Phase III upgrades for Paradise Road for the section of road between Stormont Street and Archibald Drive. The ditches have been filled to create as much room as possible for traffic through the construction zones. Traffic delays are expected as the nature of this work makes it impossible to maintain a lane of traffic in each direction all the times.
  • Adams Pond Trail: Work continues on the final section of the trail and the project is expected to be completed by the end of October. The existing section of trail is open to users with barricades placed at the construction area. Residents are asked to follow all signage and please avoid the construction area.
  • Peter Barry Duff Memorial Park: All major construction work is complete and the Park is reopen for full use effective Friday, July 19. Some electrical work is still ongoing and the lights are not yet operational. Park users are asked to follow any posted signage and avoid any identified work areas.  
Line Painting, Regular Street upgrades / paving and water and sewer work are ongoing throughout the construction season. 
Construction Project Update: July 12, 2019

Ongoing construction projects in the Town of Paradise for the period of July 15-19 include:

  • Topsail Road Roundabout: Work is now moving into Topsail Road –McNamara Drive intersection and as a result the traffic lights will be deactivated daily at 7 a.m. and return to service by 6 p.m. Traffic control will be in place while the lights are deactivated.  Traffic flow will be maintained during this portion of work – in the morning, traffic flow will be maintained eastbound with minimal interruptions until 9:00 a.m. and in the evening, traffic flow westbound will be maintained with minimal interruptions beginning at 4:00 p.m. Access to Paradise Plaza from Topsail Road is right turn only, all other traffic can access via McNamara Drive. 
  • Burnaby Drive Access: Work will be complete at the intersection of Burnaby Drive and McNamara Drive and the intersection will reopen effective end of day Friday, July 12.  
  • Clearview Heights: Road upgrades continue and the detour is in place for the duration of this construction project. 
  • Paradise Road: Work continues for Phase III upgrades to the section of road between Stormont Street and Archibald Drive. The ditches have been filled to create as much room as possible for traffic through the construction zones. Traffic delays are expected as the nature of this work makes it impossible to maintain a lane of traffic in each direction all the times.
  • Adams Pond Trail: Work continues to complete the final section of the trail the project is expected to be completed by the end of October. The existing section of trail is open to users with barricades placed at the construction area. Residents are asked to follow all signage and please avoid the construction area.
  • Peter Barry Duff Memorial Park: Work continues on light installation on the large baseball field and is expected to be completed by the end of July. The park remains closed during the day while construction is ongoing. The playground, skate park, small ballfield and soccer field are open evenings from 6 p.m. to 9 p.m. and 9 a.m. to 9 p.m. Saturday through Sunday. Park users are asked to follow all posted signage, observe all closures and avoid the construction area at the large baseball field.  
  • Camelot Crescent Playground: Work is complete and the playground is now open.  
Line Painting, Regular Street upgrades / paving and water and sewer work are ongoing throughout the construction season. 
 Construction Project Update: July 5, 2019
Ongoing construction projects in the Town of Paradise for the period of July 8-12 include:
  • Topsail Road Roundabout: Work is ongoing in the curb lanes on Topsail Road and on the road shoulders on McNamara Drive. For Topsail Road, in the morning, traffic flow will be maintained eastbound with minimal interruptions until 9:00 a.m. and in the evening, traffic flow westbound will be maintained with minimal interruptions beginning at 4:00 p.m.  Access to Paradise Plaza from Topsail Road is right turn only, all other traffic can access via McNamara Drive. 
  • Burnaby Drive Access Closed: Effective 9:00 a.m. Monday, July 8, work will be completed at the intersection of Burnaby Drive and McNamara Drive which will require closing the intersection to all traffic.  It will be closed for approximately four to five days. Traffic calming measures will be in place in Valley Ridge.
  • Clearview Heights: Road upgrades continue and the detour is in place for the duration of this construction project. 
  • Paradise Road: Work continues for Phase III upgrades to the section of road between Stormont Street and Archibald Drive. The ditches have been filled to create as much room as possible for traffic through the construction zones. Traffic delays are expected as the nature of this work makes it impossible to maintain a lane of traffic in each direction all the times.
  • Topsail Road (Christopher Street to St. Thomas Line): Minor road repairs are ongoing on Topsail Road, between Christopher Street and St. Thomas Line, including manhole repairs and paving. Minimal traffic interruptions are anticipated for this work. 
  • Adams Pond Trail: Work to complete the final section of the Adams Pond Trail begins the week of July 8, 2019.. Work will take place Monday through Friday 7:30 a.m. to 5:30 p.m. and the project is expected to be completed by the end of October. The existing trail will be open to users with barricades placed at the construction area. Residents are asked to follow all signage in the area and please avoid the construction area.
  • Peter Barry Duff Memorial Park: Work continues on light installation on the large baseball field and is expected to be completed by the end of July. The park remains closed during the day while construction is ongoing.  The playground, skate park, small ballfield and soccer field are open evenings from 6 p.m. to 9 p.m. and 9 a.m. to 9 p.m. Saturday through Sunday. Park users are asked to follow all posted signage, observe all closures and avoid the construction area at the large baseball field.  
  • Camelot Crescent Playground: The playground equipment is installed and ground work is ongoing. Weather permitting, work at the playground is expected to be completed within the next week. 
Line Painting, Regular Street upgrades / paving and water and sewer work are ongoing throughout the construction season. 
Construction Project Update: June 28, 2019

Ongoing construction projects in the Town of Paradise for the period of July 2-5 include:

  • Topsail Road Roundabout: Work is ongoing in the curb lane on Topsail Road and at the Topsail Road / McNamara Drive intersection.  In the morning, traffic flow will be maintained eastbound with minimal interruptions until 9:00 a.m. and in the evening, traffic flow westbound will be maintained with minimal interruptions beginning at 4:00 p.m.
  • McNamara Drive: Road work and sewer upgrades are finished and the first layer of asphalt is completed. The final layer of asphalt will be laid later in the summer and the Town will provide an update when that is scheduled.   
  • Clearview Heights: Road upgrades continue and the detour is in place for the duration of this construction project. 
  • Paradise Road: Work continues for Phase III upgrades to the section of road between Stormont Street and Archibald Drive. Access to Camrose Drive via Paradise Road will be unavailable beginning 7 a.m. Tuesday, July 2. Access to Camrose Drive will instead be available via Deborah Lynn Heights on St. Thomas Line. The access closure is needed as part of the Phase III Paradise Road Upgrades. Access via Paradise Road is expected to recommence on Friday, July 5.
  • Peter Barry Duff Memorial Park: Work continues on light installation on the large baseball field and is expected to be completed mid-July. The park remains closed during the day while construction is ongoing.  The playground, skate park, small ballfield and soccer field are open evenings from 6 p.m. to 9 p.m. and 9 a.m. to 9 p.m. Saturday through Sunday. Park users are asked to follow all posted signage, observe all closures and avoid the construction area at the large baseball field.  
  • Camelot Crescent Playground: The playground equipment is installed and ground work is ongoing. Weather permitting, work at the playground is expected to be completed within the next week. 

Line Painting, Regular Street upgrades/paving and water and sewer work are ongoing throughout the construction season. 

Construction Project Update: June 21, 2019
Ongoing construction projects in the Town of Paradise for the period of June 24-28 include:
  • Karwood Roundabout: All road work is finished for this project, line painting will be completed as weather permits. 
  • Topsail Road Roundabout: Work will continue in the intersection with the traffic lights deactivated intermittently as required.  Traffic control will be in place when lights are deactivated. Work will also be completed on the shoulders of the road along Topsail Road and McNamara Drive with minimal traffic interruptions are expected for this part of the work. 
  • McNamara Drive: Road work and sewer upgrades are nearing completion and work is expected to conclude in the next week. Paving operations will be scheduled as weather permits.  
  • Clearview Heights: Road upgrades continue and the detour is in place for the duration of this construction project. 
  • Paradise Road: Work continues for Phase III upgrades to the section of road between Stormont Street and Archibald Drive. 
  • Peter Barry Duff Memorial Park: Work continues on light installation on the large baseball field and is expected to be completed mid-July. The park remains closed during the day while construction is ongoing.  The playground, skate park, small ballfield and soccer field are open evenings from 6 p.m. to 9 p.m. and 9 a.m. to 9 p.m. Saturday through Sunday. Park users are asked to follow all posted signage, observe all closures and avoid the construction area at the large baseball field.  
  • Paradise Park: This project is nearing completion and the parking lot is now accessible. Park users are asked to obey signage in the area. 
  • Camelot Crescent Playground: The playground is expected to open within the next couple of weeks. The equipment is installed and ground work is ongoing. 
Line Painting, Regular Street upgrades / paving and water and sewer work are ongoing throughout the construction season. 
Construction Project Update: June 7, 2019

Ongoing construction projects in the Town of Paradise for the period of June 8-14 include:

  • Karwood Roundabout: Due to the impending forecast, paving scheduled for Saturday, June 8 is postponed. An update will be provided when the work is rescheduled. 
  • Topsail Road Roundabout: Work on the traffic lights at the intersection of Topsail Road-McNamara Drive-Clearview Heights is scheduled for Monday, June 10. The traffic lights will be deactivated at 9 a.m. and return to service by 4 p.m. Traffic control will be in place throughout the work. For the remainder of the week, working will continue along the shoulders of the road at the McNamara Drive and Topsail Road intersection. For this portion of work, no traffic interruptions are expected. 
  • McNamara Drive: Road work and sewer upgrades continue on McNamara Drive and drivers may experience traffic slowdowns. This portion of work is expected to conclude in the next couple of weeks. 
  • Clearview Heights: Road upgrades have started and a detour is in place for the duration of this construction project. 
  • Paradise Road: Work is ongoing for Phase III upgrades to the section of road between Stormont Street and Archibald Drive. The ditches have been filled to create as much room as possible for traffic through the construction zones. Traffic delays are expected as the nature of this work makes it impossible to maintain a lane of traffic in each direction all the times. 
  • Peter Barry Duff Memorial Park:  Light Installation work continues with expected completion at the end of June. 
  • Paradise Park: Work is ongoing for the installation of the new gate and it is expected to be completed by the end of June. 
Line painting, regular street upgrades / paving and water and sewer work on O’Brien’s Way are ongoing throughout the construction season. 
Construction Project Update: May 28, 2019

Ongoing construction projects in the Town of Paradise include:

  • McNamara Drive Detour: Effective Thursday, May 30, the detour through Valley Ridge subdivision will no longer be required and traffic can use McNamara Drive. Road work and sewer upgrades continue on McNamara Drive and drivers may experience traffic slowdowns.
  • Karwood Roundabout: This project is expected to conclude in the next two to three weeks, weather dependent. Westbound traffic moving from Kenmount Road into the roundabout will be limited to one lane at times during the remainder of this work as new concrete is poured. There will be a flag person at the Paradise Elementary in the morning to assist with traffic flow.
  • Paradise Road: Work began the week of May 27 for Phase III upgrades to the section of road between Stormont Street and Archibald Drive.
  • Topsail Road Roundabout: Beginning the week of June 3, work is expected to begin along the shoulders of the road at the McNamara Drive and Topsail Road intersection. For this portion of work, no traffic interruptions are expected. Additional updates on traffic impacts for this project will be provided as the work plan progresses.
  • Line Painting: The 2019 annual line painting and maintenance program is underway and will continue over the coming months and includes traffic lines, edge lines, crosswalks, stop bars, margins and arrows throughout the Town.
  • Peter Barry Duff Memorial Park Light Installation: The weather has impacted the work schedule for this project, and it is now expected to be completed the end of June.
  • Storm Sewer Cleanout on Topsail Road: This work is expected to be completed by May 31

The Town continues to work with our contractors to minimize traffic impacts as much as possible, but unfortunately traffic interruptions are unavoidable, and we ask residents for their continued patience as we work to enhance our road and transportation system. The Town will continue provide updates on construction projects throughout the work season. Please check back here for updates.