Update on the Evergreen Village Phase I Upgrade Project. Work is expected to conclude for the 2022 season in early December and will resume in Spring 2023.
The project involves Ashgrove Drive, Willow Drive and a section of Evergreen Drive (between Ashgrove Drive and Willow Drive and includes water and sewer upgrades (installation of sanitary sewer, storm sewer, and watermain infrastructure) and road upgrades on the affected streets (road, curb and gutter replacement). The project started this summer, and given the scope of the work, was planned to be completed over two construction seasons.
During the 2022 construction season, considerable progress was made on the project. The new sanitary sewer, storm sewer, catch basins, and curb and gutter were installed on Ashgrove Drive and for a portion of Willow Drive (between Ashgrove Drive and Cedar Drive). A section of homes on Ashgrove Drive (odd civic addresses) have been connected to the new sanitary sewer system.
Prior to the end of construction for this year, any driveways that have been disturbed will be reinstated and a base layer of asphalt will be placed on Ashgrove Drive, Willow Drive and the section of Evergreen Drive and crews will tidy properties in the work area. The site office trailer will remain at the corner of Willow Drive and Pinegrove Drive and all heavy equipment and materials will be removed from the site for the winter. As the area is still considered a construction site, the playground will remain closed until the full project is completed.
Phase I is expected to resume in the spring, as soon as weather permits, and the Town will issue a notice prior to work starting on site. The Town thanks residents for their patience and understanding as this infrastructure upgrade project is completed in Evergreen Village.