Posted on Friday, June 06, 2025 07:28 AM
Update - 3:40 p.m. June 6, 2025
We understand residents’ frustrations with the work on the Lanark Basketball Court. Last fall, The Town awarded the construction of the Lanark Drive basketball court to an outside contractor. The project had to be postponed when town staff identified a deficiency in the asphalt. This required the asphalt surface to be replaced.
Unfortunately, the asphalt plant only reopened for the season recently, so repairs could not begin. Repairing the asphalt is the first and...
Posted on Monday, May 26, 2025 03:02 PM
The Town of Paradise advises that construction to convert the intersection of Paddy Kay Drive and Clearview Heights into a three-way stop is scheduled to begin on Monday, May 26, 2025. The work is expected to take two days to complete, weather permitting, with crews on site from 7:00 a.m. to 5:00 p.m. each day. During this time, there may be traffic interruptions and periodic delays as crews work to complete the installation. This adjustment is being made to help improve traffic flow and...
Posted on Monday, May 26, 2025 03:00 PM
The Town of Paradise advises that the water and sewer installation on Windmill Road is scheduled to begin on Tuesday, May 27, 2025. Work will take place daily between 7:00 a.m. and 6:00 p.m. and is expected to continue for approximately 12 weeks. Due to the nature of this project, traffic interruptions and delays can be expected in the construction area. Residents on Windmill Road have been notified about the project and anticipated traffic impacts. The Town apologizes for any inconvenience...
Posted on Monday, May 26, 2025 02:58 PM
The Town of Paradise advises of lane closures for a section of St. Thomas Line. Starting Tuesday, May 27, the section of road at the intersection of Windmill Road and St. Thomas will be reduced to one lane for two weeks. Traffic control will be onsite during the day from 7:00 a.m. to 6 p.m. and temporary signal lights will be in operation when crews are offsite. The lane closure is part of the Windmill Road water and sewer upgrade project.
Crews will work to minimize delays; however, traffic...
Posted on Friday, May 16, 2025 10:36 AM
The Town of Paradise advises that construction of the temporary beach volleyball courts at Paradise Park is scheduled to begin on May 20, 2025, and will take approximately eight weeks to complete. Work will occur Monday to Friday, from 7:00 a.m. to 6:00 p.m.
For the safety of all users, the small parking lot and main gate at Paradise Park will be closed until further notice. While construction is underway, the park and accessible playground will remain open. Visitors are asked to park at the...